WG1: Preparation of Superconducing Cavities
Reducing the scatter of high-gradient EP cavities:
- analysis of measured results
- to what extent do we under stand the scatter in the results
- list and prioritise R&D activities
- identify resources to work on these activities
- describe schedule milestones
- coordinate joint effort
WG2: Technical Specifications for Infrastructures
Work out a technical specification for a future large-scale SCRF infrastructure.
WG3: Module Test-Stand
Define the scope of module test-stand activities with and without beam.
|
|
|
|
Monday, December 5, 2005
|
09:00
|
|
|
Welcome
(10')
|
Calvetti, M. (LNF)
|
|
|
09:10
|
|
Introduction and update since last meeting
(30')
document
|
Wagner, A (DESY)
|
|
|
09:40
|
|
TTF (DESY) report
(15')
document
|
Weise, H. (DESY)
|
|
|
09:55
|
|
SMTF (FNAL) report
(15')
more information
|
Lockyer, N.; presented by Padamsee, H. (Cornell Univ.)
|
|
|
10:10
|
|
STF (KEK) report
(15')
document
|
Hayano, H. (KEK)
|
|
|
10:25
|
|
|
|
10:40
|
|
XFEL status
(20')
document
|
Brinkmann, R (DESY)
|
|
|
11:30
|
|
SRF '05
(20')
document
|
Padamsee, H. (Cornell Univ.)
|
|
|
11:50
|
|
2nd ILC Workshop (Snowmass)
(20')
document
|
Walker, N. (DESY)
|
|
|
12:10
|
|
CARE SRF
(30')
document
|
Napoly, O. (Saclay)
|
|
|
12:40
|
|
WG-1 introduction
(5')
document
|
Saito, K.
|
|
|
12:45
|
|
WG-2 introduction
(5')
document
|
Matheisen, A.
|
|
|
12:50
|
|
|
|
14:30
|
|
EP History Frascati
(15')
document
|
Kneisel, P.
|
|
|
14:45
|
|
EP summary of SMTF-meeting
(15')
document
|
Tajima, T.
|
|
|
15:00
|
|
|
|
15:30
|
|
Status of EP at DESY (update)
(15')
document
|
Matheisen, A.
|
|
|
16:30
|
|
Single Cell Cavity Program in KEK
(15')
document
|
Saito, K.
|
|
|
17:00
|
|
Experience from TRISTAN
(15')
document
|
Saito, K.
|
|
|
17:15
|
|
HPR activities at INFN Milan
(15')
document
|
Michelato, P.
|
|
|
17:30
|
|
Large Grain/Single CrystalActivities at DESY
(15')
document
|
Singer, W.
|
|
Tuesday, December 6, 2005
|
09:00
|
|
Discussion topics WG1
(15')
document
|
Kneisel, P.
|
|
|
09:15
|
|
Update on Large Grain Niobium Cavities
(15')
document
|
Kneisel, P.
|
|
|
10:30
|
|
ANL Proposal to Perform Electropolishing for the ILC
(15')
document
|
Kelly, M.
|
|
|
14:30
|
|
Test program at DESY on the cryomodule test bench / test facility
(25')
more information
|
Bozhko, Y. (DESY)
|
|
|
14:55
|
|
Status and plans for the ILC Cryomodule design
(25')
document
|
Petersen, T. (FNAL)
|
|
|
15:15
|
|
Beam plan at STF phase1
(15')
document
|
Hayano, H.
|
|
|
15:30
|
|
Preliminary results from TTF HOM BPM system
(15')
document
|
Ross, M.
|
|
|
15:45
|
|
Status of ILCTA@ Fermilab and plans for beam tests
(15')
document
|
Nagaitsev, S.
|
|
|
16:30
|
|
|
Status of ILCTA@Fermilab and plans for tests with/without beams
(20')
|
Nagaitsev, S. (FNAL)
|
|
|
16:50
|
|
Beam measurements at TTF
(20')
document
|
Weise, H. (DESY)
|
|
|
17:10
|
|
|
Planned beam measurements at STF
(20')
|
Hayano, H. (KEK)
|
|
Wednesday, December 7, 2005
|
09:00
|
|
Report from Collaboration Board
(20')
document
|
Wagner, A (DESY)
|
|
|
09:20
|
|
Report from Technical Board
(20')
document
|
Edwards, H. (FNAL)
|
|
|
09:40
|
|
|
|
10:10
|
|
WG-2 summary
(20')
document
|
Higo, T (KEK)
|
|
|
10:30
|
|
WG-3 summary
(20')
document
|
Petersen, B. (DESY)
|
|
|
10:50
|
|
|
closing remarks
(5')
|
Guidicci, S. (LNF)
|
|
|