Commissioning status - beam and optics tuning

  1. Performance of High Beta Optics Beam Tuning
  2. ATF Operation

Critical review of achievements and shed light on issues to be studied

  1. Performance of BPM system ( C- , S-band and stripline BPMs)
  2. Performance of 5 wire scanner system
  3. Performance of Shintake monitor
  4. Alignment

Milestones in 2009-2010

  1. sub-micron beam size
  2. ILC scaled &sigmay=75nm
  3. Design &sigmay=37nm
  4. 2nm resolution of IP BPM
  5. FONT IP feedback commissioning for nm stability of IP position

Future Plan in 2010 -

  1. Generation of ILC like bunch train Pushed beta R&D
    • study at present configuration for Eduardo MARIN LACOMA's (CERN) Doctor degree
    • SC-QD0 and a new QF1 with larger aperture
  2. SC-FD

The 9th ATF TB/SGC Meeting

The 9th ATF TB/SGC will be held at 14:00 -, 17th December after the project meeting at KEK, and the Year-End Party will be thrown on evening of 17th December.